Stuck with a stores, inventory, MRP or scheduling problem in your factory? Ask here. I answer every question for free, and the answers are shared below so other manufacturers can learn too.
Answered questions
StoresPhysical stock never matches the system stock. Where do I start?
Do not start with a full stock-taking. Start with discipline at the counter: nothing enters or leaves the store without an entry, and only one person makes entries in each shift.
Then count a small set every week. Take your top 50 items by value (A items) and count 10 of them each week. When a count does not match, write down the reason (issued without slip, wrong unit, rejection not booked).
After 4–6 weeks the reasons show a pattern. Fix those 2–3 reasons and the gap starts closing for every item, not only the counted ones.
InventoryHow do I decide the reorder level for a bought-out part?
Reorder level = average daily use × supplier lead time in days + safety stock.
Example: you use 40 pieces a day, the supplier takes 10 days, and sometimes 3 days late. Reorder level = 40 × 10 + 40 × 3 = 520 pieces.
Review it every month for your A items, because daily use and supplier lead time both change. A reorder level fixed two years ago is one of the most common reasons for shortages.
MRPIs MRP only for big companies with ERP software?
No. MRP is a calculation, not software. You need four things: the bill of materials, current stock, open purchase orders, and your customer orders with dates.
Net requirement = what the orders need − stock in hand − material already ordered + safety stock. If the answer is positive, that is what you must buy, and the order date is the need date minus the lead time.
For a shop with up to a few hundred items, this works well in Excel. Software helps when the volume grows, but the logic is the same.
SchedulingAll my machines look busy, but orders are still late. Why?
Usually one machine or process decides the output of the whole shop. This is the bottleneck. Every hour lost there is an hour lost for the full factory; an hour lost on other machines often costs nothing.
Find it by looking where jobs wait the longest. Then plan that machine first, keep it running in breaks and shift changes, and release work to other machines only as fast as the bottleneck can take it.
Loading every machine to 100% only builds piles of half-finished jobs, which hides the real problem.
InventoryWhat should I do with slow-moving and dead stock?
First, make the list: items with no issue in the last 180 days, with quantity and value. Most owners are surprised by the total.
Sort each item into one of four groups: will be used in a known order, can be reworked into a running part, can be sold back or sold as scrap, or must be written off.
Most important: find why it was bought. Usually it is a design change, a cancelled order, or minimum order quantity. Fixing that stops new dead stock.
PlanningWhat is a material readiness check?
A job is ready to start only when every material it needs is actually available. Releasing a job to the shop floor before that only creates half-built work that sits and waits.
A simple daily routine: check each order planned for the next 1–2 weeks against stock, mark it ready or short, and send the short list to purchase every morning.
This one habit cuts a lot of firefighting, because the floor only works on what can be finished.